Deep Marine Technology’s 292ft DMT Emerald vessel has successfully installed a purpose built suction pile, subsea manifold, and tree for a major oil company utilizing its 100T Multi-purpose Tower. The suction pile, over 35ft tall and 15ft in diameter, was successfully over boarded in 4ft to 6ft seas and installed in under 12 hours.
The pile was landed at the desired location in 5,000 fsw, and completed in 66% of the allotted time given by the client.
The DMT Emerald crew additionally installed a manifold and set a tree. The manifold weighing over 35 tons was successfully installed onto the suction pile ahead of schedule and without any issues. The tree weighing 48 tons and measuring 15ft X 15ft X 20ft tall was set via keel haul transferred to the 100T Multi-purpose Tower. It was set in approximately 10 hours from water to landed, ahead of client expectations.
The DP II, DMT Emerald includes the 100T Multi-purpose Tower, a 100T Knuckle Boom Crane, a 23ft X 27ft moon pool, accommodations for 73, and is outfitted with two 150Hp, 10,000 fsw Triton® XLS work class Remotely Operated Vehicles (ROVs).
Photo://DMT
The FPSO Sevan Piranema has today commenced oil production on the Piranema field, off the coast of Aracaju, in the state of Sergipe, Brasil.
Q is located in Mississippi Canyon block 961. The natural gas field is developed as a subsea tieback to the Anadarko-operated Independence Hub facility in the eastern US Gulf of Mexico. StatoilHydro has a 50% working interest in the Q field.
The Piranema field, 25 km off the coast of Sergipe, started producing oil this Wednesday (10/10), in deep Northeastern Brazil waters. With operations going online in this field, Petrobras is taking another step towards maintaining Brazil’s oil self-sufficiency. The Piranema oil, of excellent quality, at 44º API, is the lightest oil produced in deep waters in Brazil.
The first tanker with a cargo of liquefied natural gas (LNG) from the Snøhvit field left port at Melkøya near Hammerfest, northern Norway
Exxon Mobil Corporation (NYSE:XOM) announced today that its subsidiary, Esso Exploration Angola (Block 15) Limited, has started production from the Marimba North project, designed to develop 80 million barrels of oil in approximately 3,900 feet (1,300 meters) of water more than 90 miles (145 kilometers) off the coast of Angola.